Service performance
How many decisions NITDA makes by each service’s deadline, and what it has issued.
Decisions made on time
Each service’s deadline comes from the instrument named under it: the NITDA Service Charter 2026 or the instrument the service rests on. Where no instrument sets a time, Digital Assurance uses a default that NITDA can change, shown as “platform default”. A default approval is a decision Digital Assurance made because NITDA did not acknowledge an application in time.
Decisions from October to December 2026
| Service | Decided | On time | Share on time | Default approvals |
|---|---|---|---|---|
| .gov.ng and .mil.ng domain registration and updatesDeadline: Service Charter 2026 | 1 | 1 | 100% | 0 |
| AppealsDeadline: platform default | 1 | 1 | 100% | 0 |
| Digital infrastructure certification (NDIAF)Deadline: NDIAF 2026 | 11 | 11 | 100% | 0 |
| Enforcement and sanctionsNo set deadline | 3 | 3 | 100% | 0 |
| IT Project ClearanceDeadline: Clearance guideline 2026 and Service Charter 2026 | 14 | 13 | 93% | 6 |
| Partnership (PPP) proposalDeadline: platform default | 1 | 1 | 100% | 0 |
| Periodic audit reportDeadline: platform default | 1 | 1 | 100% | 0 |
| Quality assurance and completionDeadline: platform default | 5 | 5 | 100% | 0 |
| Training enrolmentNo set deadline | 6 | 6 | 100% | 0 |
| Trustmark verifier certificationDeadline: platform default | 1 | 1 | 100% | 0 |
| All services | 44 | 43 | 98% | 6 |
Decisions from July to September 2026
| Service | Decided | On time | Share on time | Default approvals |
|---|---|---|---|---|
| .gov.ng and .mil.ng domain registration and updatesDeadline: Service Charter 2026 | 4 | 4 | 100% | 0 |
| Certification authority half-yearly reportDeadline: platform default | 1 | 1 | 100% | 0 |
| Compliance assurance firm licenceDeadline: platform default | 4 | 4 | 100% | 0 |
| Device type approvalDeadline: platform default | 1 | 1 | 100% | 0 |
| Digital infrastructure certification (NDIAF)Deadline: NDIAF 2026 | 8 | 8 | 100% | 0 |
| Enforcement and sanctionsNo set deadline | 1 | 1 | 100% | 0 |
| Information security audit report (draft instrument)Deadline: platform default | 2 | 2 | 100% | 0 |
| Innovation programme callsNo set deadline | 3 | 3 | 100% | 0 |
| Intervention requestDeadline: platform default | 1 | 1 | 100% | 0 |
| Intervention use reportDeadline: platform default | 3 | 3 | 100% | 0 |
| IT Project ClearanceDeadline: Clearance guideline 2026 and Service Charter 2026 | 33 | 31 | 94% | 0 |
| MISP threat-sharing membershipDeadline: platform default | 4 | 4 | 100% | 0 |
| OEM batch reportDeadline: platform default | 2 | 2 | 100% | 0 |
| Partnership (PPP) proposalDeadline: platform default | 1 | 1 | 100% | 0 |
| Petition to the anti-corruption unitDeadline: platform default | 2 | 2 | 100% | 0 |
| PIA compliance reportDeadline: platform default | 1 | 1 | 100% | 0 |
| QA report for a milestoneDeadline: platform default | 21 | 21 | 100% | 0 |
| Quality assurance and completionDeadline: platform default | 21 | 21 | 100% | 0 |
| Software testing organisation licence (LSTO)Deadline: Testing organisations licensing guideline 2026 | 4 | 4 | 100% | 0 |
| Startup labellingDeadline: platform default | 1 | 1 | 100% | 0 |
| Supplier listingDeadline: platform default | 65 | 65 | 100% | 0 |
| Training enrolmentNo set deadline | 8 | 8 | 100% | 0 |
| All services | 191 | 189 | 99% | 0 |
Decisions from April to June 2026
| Service | Decided | On time | Share on time | Default approvals |
|---|---|---|---|---|
| .gov.ng and .mil.ng domain registration and updatesDeadline: Service Charter 2026 | 4 | 3 | 75% | 0 |
| Approval to host a government website or government data outside NigeriaDeadline: platform default | 1 | 1 | 100% | 0 |
| Compliance assurance firm licenceDeadline: platform default | 2 | 2 | 100% | 0 |
| Information security audit report (draft instrument)Deadline: platform default | 1 | 1 | 100% | 0 |
| Intervention requestDeadline: platform default | 1 | 1 | 100% | 0 |
| Intervention use reportDeadline: platform default | 3 | 3 | 100% | 0 |
| IT company registration (IICP)Deadline: Service Charter 2026 | 4 | 4 | 100% | 0 |
| IT Project ClearanceDeadline: Clearance guideline 2026 and Service Charter 2026 | 70 | 63 | 90% | 0 |
| MISP threat-sharing membershipDeadline: platform default | 2 | 2 | 100% | 0 |
| Nigeria Digital TrustmarkDeadline: platform default | 1 | 1 | 100% | 0 |
| PIA compliance reportDeadline: platform default | 1 | 1 | 100% | 0 |
| Platform annual compliance reportDeadline: platform default | 2 | 2 | 100% | 0 |
| QA report for a milestoneDeadline: platform default | 16 | 16 | 100% | 0 |
| Supplier listingDeadline: platform default | 57 | 57 | 100% | 0 |
| Training enrolmentNo set deadline | 8 | 8 | 100% | 0 |
| All services | 173 | 165 | 95% | 0 |
Decisions from January to March 2026
| Service | Decided | On time | Share on time | Default approvals |
|---|---|---|---|---|
| .gov.ng and .mil.ng domain registration and updatesDeadline: Service Charter 2026 | 4 | 4 | 100% | 0 |
| Approval to host a government website or government data outside NigeriaDeadline: platform default | 1 | 1 | 100% | 0 |
| Certification authority half-yearly reportDeadline: platform default | 1 | 1 | 100% | 0 |
| Device type approvalDeadline: platform default | 1 | 1 | 100% | 0 |
| Intervention requestDeadline: platform default | 1 | 1 | 100% | 0 |
| Intervention use reportDeadline: platform default | 2 | 2 | 100% | 0 |
| IT company registration (IICP)Deadline: Service Charter 2026 | 20 | 20 | 100% | 0 |
| IT Project ClearanceDeadline: Clearance guideline 2026 and Service Charter 2026 | 50 | 47 | 94% | 0 |
| MISP threat-sharing membershipDeadline: platform default | 1 | 1 | 100% | 0 |
| Multinational local content plan and CSR noticesDeadline: platform default | 1 | 1 | 100% | 0 |
| NITDEF scholarshipNo set deadline | 8 | 8 | 100% | 0 |
| OEM factory evidenceDeadline: platform default | 1 | 1 | 100% | 0 |
| PIA compliance reportDeadline: platform default | 3 | 3 | 100% | 0 |
| Registration of investors, accelerators and hubsDeadline: platform default | 1 | 1 | 100% | 0 |
| Supplier listingDeadline: platform default | 39 | 39 | 100% | 0 |
| All services | 134 | 131 | 98% | 0 |
Earlier quarters
Decisions from October to December 2025
| Service | Decided | On time | Share on time | Default approvals |
|---|---|---|---|---|
| Data centre operator registrationDeadline: platform default | 1 | 0 | 0% | 0 |
| Device type approvalDeadline: platform default | 1 | 1 | 100% | 0 |
| Government network audit and information security audit returnsDeadline: platform default | 10 | 10 | 100% | 0 |
| Intervention requestDeadline: platform default | 1 | 1 | 100% | 0 |
| IT company registration (IICP)Deadline: Service Charter 2026 | 51 | 51 | 100% | 0 |
| Public Internet Access provider registration and compliance reportsDeadline: platform default | 1 | 1 | 100% | 0 |
| Trustmark verifier certificationDeadline: platform default | 1 | 1 | 100% | 0 |
| All services | 66 | 65 | 98% | 0 |
Decisions from July to September 2025
| Service | Decided | On time | Share on time | Default approvals |
|---|---|---|---|---|
| Certification authority half-yearly reportDeadline: platform default | 1 | 1 | 100% | 0 |
| Device type approvalDeadline: platform default | 1 | 1 | 100% | 0 |
| Intervention requestDeadline: platform default | 2 | 2 | 100% | 0 |
| IT company registration (IICP)Deadline: Service Charter 2026 | 1 | 1 | 100% | 0 |
| OEM evidence of operations and ISO 9001:2015Deadline: platform default | 1 | 1 | 100% | 0 |
| Platform profile and annual compliance reportDeadline: platform default | 2 | 2 | 100% | 0 |
| Public Internet Access provider registration and compliance reportsDeadline: platform default | 1 | 1 | 100% | 0 |
| Registration of investors, accelerators and hubsDeadline: platform default | 1 | 1 | 100% | 0 |
| All services | 10 | 10 | 100% | 0 |
Decisions from April to June 2025
| Service | Decided | On time | Share on time | Default approvals |
|---|---|---|---|---|
| Data centre operator registrationDeadline: platform default | 1 | 0 | 0% | 0 |
| Device type approvalDeadline: platform default | 1 | 1 | 100% | 0 |
| e-Invoicing access point provider accreditationDeadline: e-Invoicing guideline 2025 | 1 | 0 | 0% | 0 |
| PIA compliance reportDeadline: platform default | 1 | 1 | 100% | 0 |
| Platform profile and annual compliance reportDeadline: platform default | 1 | 1 | 100% | 0 |
| Registration of investors, accelerators and hubsDeadline: platform default | 1 | 1 | 100% | 0 |
| All services | 6 | 4 | 67% | 0 |
Decisions from January to March 2025
| Service | Decided | On time | Share on time | Default approvals |
|---|---|---|---|---|
| Certification authority (sub-CA) accreditationDeadline: platform default | 1 | 0 | 0% | 0 |
| Data centre operator registrationDeadline: platform default | 1 | 0 | 0% | 0 |
| IT company registration (IICP)Deadline: Service Charter 2026 | 6 | 6 | 100% | 0 |
| Public Internet Access provider registration and compliance reportsDeadline: platform default | 1 | 1 | 100% | 0 |
| Startup labellingDeadline: platform default | 1 | 1 | 100% | 0 |
| All services | 10 | 8 | 80% | 0 |
Decisions from October to December 2024
| Service | Decided | On time | Share on time | Default approvals |
|---|---|---|---|---|
| Device type approvalDeadline: platform default | 1 | 1 | 100% | 0 |
| OEM evidence of operations and ISO 9001:2015Deadline: platform default | 1 | 1 | 100% | 0 |
| All services | 2 | 2 | 100% | 0 |
Decisions from July to September 2024
| Service | Decided | On time | Share on time | Default approvals |
|---|---|---|---|---|
| Data centre operator registrationDeadline: platform default | 1 | 0 | 0% | 0 |
| IT company registration (IICP)Deadline: Service Charter 2026 | 2 | 2 | 100% | 0 |
| OEM factory evidenceDeadline: platform default | 1 | 1 | 100% | 0 |
| OEM licence and re-certificationDeadline: platform default | 1 | 0 | 0% | 0 |
| All services | 5 | 3 | 60% | 0 |
Decisions from April to June 2024
| Service | Decided | On time | Share on time | Default approvals |
|---|---|---|---|---|
| Startup labellingDeadline: platform default | 1 | 1 | 100% | 0 |
| All services | 1 | 1 | 100% | 0 |
Decisions from January to March 2024
| Service | Decided | On time | Share on time | Default approvals |
|---|---|---|---|---|
| OEM factory evidenceDeadline: platform default | 1 | 1 | 100% | 0 |
| All services | 1 | 1 | 100% | 0 |
Decisions from October to December 2023
| Service | Decided | On time | Share on time | Default approvals |
|---|---|---|---|---|
| OEM licence and re-certificationDeadline: platform default | 1 | 0 | 0% | 0 |
| All services | 1 | 0 | 0% | 0 |
Issued and in force
- Licences and registrations in force
- 134
- Registered indigenous IT companies (IICP): 85
- Licensed original equipment manufacturers (OEMs): 4
- Registered data centre operators: 3
- Certified digital infrastructure providers (NDIAF): 18
- Registered Public Internet Access providers: 3
- Licensed compliance assurance firms: 6
- Licensed software testing organisations: 4
- Accredited e-invoicing system integrators: 1
- Accredited e-invoicing access point providers: 1
- Accredited certification authorities: 1
- Nigeria Digital Trustmark holders: 1
- Certified Trustmark verifiers: 1
- Labelled startups: 3
- Registered investors, accelerators and hubs: 3
- Certified products
- 103
- Cleared government IT projects
- 158